Purpose
South Jordan City and the Utah Department of Transportation are reconstructing 2200 West between 9400 South and 11400 South to create a consistent corridor that will increase motorist and pedestrian safety and improve walkability.
Improvements
Improvements include:
- 11 feet lanes with a 13 feet center median
- Consistent curb, gutter, sidewalk, and a 5 feet park strip
- An improved storm drain system
- Improved roadway shoulders
Remaining Construction Activities
The remaining construction activities are as follows:
- Street Lights installed and operating by Spring 2022
- Landscaping to be completed Summer 2022
Stay Informed
The Public Information Team is available to answer questions or address concerns from the community. Please contact the Utah Department of Transportation (UDOT):