Construction Projects – South Jordan

Construction Projects

Purpose: Addition of northbound right turn lane (by America First Bank) and southbound right turn lane (by Burger King) on River Heights Drive.

Duration: The northbound right turn lane is complete. Construction of the southbound right turn lane (by Burger King) will resume Spring 2020.

Location: River Heights and South Jordan Parkway

Funding: Salt Lake County

Impact: Minor traffic on collector roads, potential for hazards, daytime noise

Images & Maps:

 

Purpose: Installation of a 14” PVC secondary waterline from Dunsinane Drive to 4800 W.

Duration: The installation of the secondary waterline will start on February 17, 2020. Completion of the project is expected late Spring 2020.

Location:  10200 S from Dunsinane Drive to 4800 W

Impact: 10200 S between 4000 W & Gilly Street will be closed May 6th and May 8th between the hours of 7:00 AM and 4:00 PM. Northbound lanes on 4000 W will be shifted.

Funding: Water Fund

Images & Maps:

 

Purpose: Replace transite pipeline with new PVC pipeline

Duration: Mill and overlay of Bonanza Circle, Bonanza Way, and Bonanza Court will take place Spring 2020. Installation of the waterline on Horseshoe Circle will resume Spring 2020.

Location: Bonanza Circle and Horseshoe Circle

Impacts: Construction will begin March 3rd on Horseshoe Circle until approximately April 3rd. The road will have a soft closure with barricades up from 7:30 AM to 5:00 PM. Please expect minor traffic issues, potential hazards, and daytime noise.

Funding: Water fund

Maps & Images:


Purpose: To construct 6 new pickleball courts, install restrooms and upgrade the pavilion at City Park

Duration: Completion scheduled for Spring 2020

Location: City Park

Impacts: The construction areas are fenced, so the pavilion and existing playground are not available for use.

Maps & Images:

Purpose: Installation of 42″ steel waterline by Jordan Valley Water Conservancy District in 10200 South from Dunsinane Dr. to approximately 5700 West.

Duration: Construction will begin February 18, 2020 and end approximately August 2020.

Location: 10200 S from 4000 W to Yorkshire Dr.

Impacts: The intersection of 10200 S & 4800 W will be closed starting May 6th at 7:00 AM and will reopen by 5:00 PM on May 8th.

May 11th through May 15th, there will be temporary traffic signals located in the intersection of 10200 S & 4800 W. North and south bound traffic will be allowed. West bound traffic will be detoured north. East bound traffic will not be allowed and will be detoured to South Jordan Parkway.

May 18th,  10200 S will be closed (200 ft. at a time) moving west of 4800 W.

Drivers and pedestrians shall use caution while traveling in a work zone. Please expect some traffic delays on minor collector roads, the potential for hazards, and daytime noise.

Images & Maps:

Purpose: This project is being done to create a wetland education center to enhance the nature of the site and provide public accessibility.

Duration: Data gathering will start the beginning of March 2020. There is not a construction start date for this project.

Location:  947 W Shields Lane

Impact: There are no impacts identified at this time.

Funding: NA

Images & Maps:

Purpose: The roadway improvements include: construction of sidewalk, curb, and gutter, under-grounding the power, addition of a bike lane, and new striping.

Duration: Construction starts March 9th. Completion of the project is expected by the end of June 2020.

Location: 2700 W from 11400 S to 11625 S

Funding: Salt Lake County

Impact: Construction will be from March 9th to June 2020 from 7:00 AM – 5:00 PM. Please expect some traffic delays on minor collector roads, potential for hazards, and daytime noise.

Images & Maps:

Purpose: The project is being done to construct a drinking water pipeline to replace existing aging pipe at the intersection of 1300 W 10875 S.

Duration: Construction will start on March 31st and last through April 8th.

Location: 1300 W & 10875 S Intersection

Funding: Culinary Water

Impact: There will be traffic impacts to drivers traveling northbound and southbound on 1300 W.

Images & Maps:

Purpose: This project is being done to install a new storm drain line.

Duration: The project will begin on April 21, 2020 and end on approximately May 4, 2020.

Location: Millerton Dr. from 10200 S to Clark Hills Dr. (10465 S).

Funding: Storm Drain Fund

Impact: Millerton Dr. will be closed in sections periodically (up to a few hours at a time) throughout the next two weeks between the hours of 8:00 AM and 4:00 PM. The contractor will provide residents access to their homes at all times, but the road will be closed to through traffic. Drivers traveling on Millerton Dr. be detoured.

Images & Maps:

Purpose: The contractor for Clover Ridge 3 (new subdivision) will be repairing the road.

Duration: The project will begin on May 7th at 7:00 AM and end the evening of May 11th.

Location: A portion of Country Ridge Drive.

Impact: The road will remain closed the entire length of time, including nights.

Images & Maps:

Purpose: The project will install new sidewalk, as well as traditional curb and gutter, along the east side of this segment to improve pedestrian safety. In order to achieve this, this section of 3200 West will also need to be slightly widened to the west, to make room for the new east-side elements. Some drainage improvements and utility adjustments are also included in the project.

Duration: The project is scheduled to begin on Tuesday, May 26th.

Location: 3200 W from 10431 S to 10600 S

Funding: Federal Funding

Impact:

  • During construction, motorists should anticipate minor travel delays during work hours, 7 a.m. to 5 p.m. Monday through Friday.
  • One lane will remain open in each direction the majority of the time, but there will be intermittent occurrences of one-way traffic guided by flaggers.
  • There will be NO LEFT TURNS from northbound or southbound 3200 West onto 10400 South.
  • The sidewalk will be closed on the west side of the work zone. Pedestrians should plan to use an alternate route.
  • Property and business access along the corridor will be maintained.

For more information please visit UDOT’s Website.

Images & Maps:

City Projects Map:

Stay up to date with all the South Jordan City Projects. Using the link below, you can click on the colored icons to find the name, description and status of all the active projects in the City.
Projects Map