Construction Projects – South Jordan

Construction Projects

Purpose: Addition of northbound right turn lane (by America First Bank) and southbound right turn lane (by Burger King) on River Heights Drive.

Duration: The northbound right turn lane is complete. Construction of the southbound right turn lane (by Burger King) will resume Spring 2020.

Location: River Heights and South Jordan Parkway

Funding: Salt Lake County

Impact: Minor traffic on collector roads, potential for hazards, daytime noise

Images & Maps:

 

Purpose: Installation of a 14” PVC secondary waterline from Dunsinane Drive to 4800 W.

Duration: The installation of the secondary waterline will start on February 17, 2020. Completion of the project is expected late Spring 2020.

Location:  10200 S from Dunsinane Drive to 4800 W

Impact: The contractor will have traffic control on 10200 S between Yorkshire Dr and Tranmere Ave from March 30th to April 3rd between 8:00 AM and 5:00 PM. Local traffic will be accommodated.

Traffic control will also be utilized at the intersection of 10200 S and 4800 W from March 31st to April 2nd between 8:00 AM and 5:00 PM. The traffic control is as follow:

  • There will be two traveling lanes at 10200 S – eastbound and westbound.
  • Right turn into 4800 W traveling westbound on 10200 S will not be allowed.
  • Left turn into 4800 W traveling eastbound on 10200 S will not be allowed.
  • Traffic traveling northbound on Silver Mine will be allowed to turn only left or right. Through traffic traveling northbound from Silver Mine to 4800 W will not be allowed.
  • 4800 W will maintain the southbound travel lane open.

Funding: Water Fund

Images & Maps:

Purpose: Replace transite pipeline with new PVC pipeline

Duration: Mill and overlay of Bonanza Circle, Bonanza Way, and Bonanza Court will take place Spring 2020. Installation of the waterline on Horseshoe Circle will resume Spring 2020.

Location: Bonanza Circle and Horseshoe Circle

Impacts: Construction will begin March 3rd on Horseshoe Circle until approximately April 3rd. The road will have a soft closure with barricades up from 7:30 AM to 5:00 PM. Please expect minor traffic issues, potential hazards, and daytime noise.

Funding: Water fund

Maps & Images:


Purpose: To construct 6 new pickleball courts, install restrooms and upgrade the pavilion at City Park

Duration: Completion scheduled for Spring 2020

Location: City Park

Impacts: The construction areas are fenced, so the pavilion and existing playground are not available for use.

Maps & Images:

Purpose: South Valley Sewer District is installing a 15” sewer line.

Duration: Construction will begin January 24, 2020 and end approximately on February 24, 2020.

Location: River Heights Dr. from 10400 S to 10534 S

Impacts: Temporary traffic signals will be in place allowing one way traffic north and south.  This traffic control setup will be in place until February 26, 2020.

Maps & Images:

Purpose: Installation of 42″ steel waterline by Jordan Valley Water Conservancy District in 10200 South from Dunsinane Dr. to approximately 5700 West.

Duration: Construction will begin February 18, 2020 and end approximately August 2020.

Location: 10200 S from 4000 W to Yorkshire Dr.

Impacts: 10200 S from 4000 W to Yorkshire Dr. will be closed for two weeks (April 3rd – 17th), see traffic control below. The road will not be opened at the end of the day in the main work zone (600-ft section), so traffic control will stay in place.

Drivers and pedestrians shall use caution while traveling in a work zone. Please expect some traffic delays on minor collector roads, the potential for hazards, and daytime noise.

Images & Maps:

Purpose: Gough Construction will be closing Kestrel Rise Road between Dock Street & Split Rock Drive for a subdivision development.

Duration: February 24th to February 28th

Location: Kestrel Rise Road between Dock Street & Split Rock Drive

Funding: NA

Impact: The closure will happen from February 24th to February 28th. The road will remain closed at night for the five days.

Images & Maps:

Purpose: Summit Line Construction is upgrading and rebuilding an existing transmission line.

Duration: February 25th through March 2nd

Location: 11000 S Woodfield Drive, 11150 S 1494 W, and 10760 S Beckstead Lane

Funding: NA

Impact: On March 2nd, 10760 S Beckstead Lane will be closed at 7:00 AM and remain closed until Wednesday, March 4th at 5:00 PM.

Images & Maps:

Purpose: This project is being done to create a wetland education center to enhance the nature of the site and provide public accessibility.

Duration: Data gathering will start the beginning of March 2020. There is not a construction start date for this project.

Location:  947 W Shields Lane

Impact: There are no impacts identified at this time.

Funding: NA

Images & Maps:

Purpose: The roadway improvements include: construction of sidewalk, curb, and gutter, under-grounding the power, addition of a bike lane, and new striping.

Duration: Construction starts March 9th. Completion of the project is expected by the end of June 2020.

Location: 2700 W from 11400 S to 11625 S

Funding: Salt Lake County

Impact: Construction will be from March 9th to June 2020 from 7:00 AM – 5:00 PM. Please expect some traffic delays on minor collector roads, potential for hazards, and daytime noise.

Images & Maps:

Purpose: The project is being done to construct a drinking water pipeline to replace existing aging pipe at the intersection of 1300 W 10875 S.

Duration: Construction will start on March 31st and last through April 8th.

Location: 1300 W & 10875 S Intersection

Funding: Culinary Water

Impact: There will be traffic impacts to drivers traveling northbound and southbound on 1300 W.

Images & Maps:

City Projects Map:

Stay up to date with all the South Jordan City Projects. Using the link below, you can click on the colored icons to find the name, description and status of all the active projects in the City.
Projects Map