Construction Projects

Upcoming Impacts

Beginning on Monday, September 13, 2021, crews will begin installing several sewer bypass lines throughout Riverfront Parkway in South Jordan. This work will require lane closures throughout the corridor for up to three weeks. Drivers may experience short delays in the area. Access to residents and businesses will be maintained.

  1. On Monday, September 13, crews will begin work between 11400 South and W 11490 S on Riverfront Parkway. This work is anticipated to finish on Thursday, September 23.
    1. Drivers can anticipate traffic shifted to west of the road way to accommodate the work zone on the east side of the roadway. Please follow all posted signage.
  2. On Monday, September 13, crews will begin work between 11400 South and Palisade Drive on Riverfront Parkway. This work is anticipated to finish on Monday, September 20.
    1. Drivers can anticipate a full northbound lane closure between Thursday, September 16 and Monday September 20 to accommodate the work zone. Drivers are encourage to follow detour signage.
    2. The northern parking lot entrance to the East River Front Park will be closed.
  3. On Thursday, September 16, crews will begin work between the Ventris building and 10600 South on Riverfront Parkway. This work is anticipated to finish on Thursday, September 23.
    1. Drivers can anticipate left northbound and southbound lane closures to accommodate the work zone.
    2. Left turns will be restricted at each intersection throughout the corridor.
  4. On Thursday, September 16, crews will begin between the Café Zupas building and the JCW’s building on Riverfront Parkway. This work is anticipated to finish on Saturday, September 18,.
    1. Drivers can anticipate northbound and southbound lanes shifted to the east side of the roadway and a one lane closure in each direction.
    2. Left turns will be restricted at intersection throughout the corridor.
    3. The driveway entrance to Café Zupas, Barbacoa, and JCW’s will be closed for the duration of this work. Please use the alternative entrances for Mountain America Credit Union or the road just south of Café Zupas to access these businesses.

What to Expect

  • Work hours will be 24 hours a day, Monday through Friday.
  • Parking restrictions may be required. All restrictions will be posted no less than 2 days prior to taking effect and being enforced.
  • Lane closures throughout the area.
  • Driveway access will be maintained for each property.
  • Increased noise, dirt, and lighting.
  • Drivers are encouraged to follow all posted signage to ensure the safety of the public and crews.

Anticipated Schedule

Week of September 6

  • Crews will continue work at 909 UT 151 in South Jordan
  • This work is anticipated to finish on Friday, September 10

Week of September 13 & September 20

  • Crews will begin work at 114 South and River Front Parkway in South Jordan
  • Crews will begin work at 10769 S River Front Parkway in South Jordan
  • This work is anticipated to finish on Wednesday, September 29

Week of September 27

  • Crews will begin work at 14532 South 1515 West Bluffdale
  • This work is anticipated to finish on Saturday, October 2

Week of October 18

  • Crews will begin work at 689 South Jordan Parkway
  • This work is anticipated to finish on Saturday, October 23

The schedule is subject to change given weather and other unforeseen impacts.

CURRENT CONSTRUCTION ACTIVITIES
Construction activities for Tuesday, September 7 through Friday, September 10, 2021 are as follows:

Crews are working on the final punchlist items before completing the project. We anticipate just a couple more weeks of work remain. Work items include the remainder of the mailbox installation, final stamped concrete in the park strip, and clean up work.

Separate crews, hired by South Jordan City, began work on the new roadway asphalt.

Purpose: South Jordan City and the Utah Department of Transportation are reconstructing 2200 West between 9400 South and 11400 South to create a consistent corridor that will increase motorist and pedestrian safety and improve walkability. 

Improvements include:

  • 11’ lanes with a 13’ center median
  • Consistent curb, gutter, sidewalk, and a 5’ park strip
  • An improved storm drain system
  • Improved roadway shoulders

Duration: Construction is expected to be completed in early fall 2021.

Location: 2200 W  –  9400 South to 11400 South

Impact: Surrounding residents and businesses can expect narrowed lanes, congestion during times of heavy travel, construction equipment and vehicles in the area, and an increase in noise, dust and vibration.

Please be alert and follow the traffic changes when traveling through the construction zone. The lanes will remain narrowed through the duration of the project and may shift, as needed.

Images & Maps:

Stay Informed
The Public Information Team is available to answer questions or address concerns from the community. Please contact UDOT:

Hotline: 385.955.2846
Email: 2200west@utah.gov
Web: www.udot.utah.gov/go/2200west

TRAX South Jordan Parkway Station Detour

South Jordan City and Larry H. Miller Group are extending Lake Run Road and building a Grandville Avenue intersection. This will result in alternative pedestrian access to the South Jordan Parkway Station. Use the following information to plan your trip:

  • Dates:
    • September 27 – October 1
  • Service:
    • Full vehicle, parking, and pedestrian access to the station
    • Use the temporary pedestrian trail (see map)
    • No access to the South entrance
    • Use the North entrance to enter and exit the station
  • Plan Ahead:
    • Give yourself an extra 5-10 minutes to get to the station
  • Train Schedule:
  • Construction Alerts:

Red Line Disclaimer
South Jordan Parkway Station pedestrian path and South entrance is closed due to city road construction. Use the temporary path and North entrance to access the station. Visit www.rideuta.com/construction for details.

City Projects Map:

Stay up to date with all the South Jordan City Projects. Using the link below, you can click on the colored icons to find the name, description and status of all the active projects in the City.
Projects Map