Construction Projects – South Jordan

Construction Projects

Purpose: Addition of northbound right turn lane (by America First Bank) and southbound right turn lane (by Burger King) on River Heights Drive.

Duration: The northbound right turn lane is complete. Construction of the southbound right turn lane (by Burger King) will resume Spring 2020.

Location: River Heights and South Jordan Parkway

Funding: Salt Lake County

Impact: Minor traffic on collector roads, potential for hazards, daytime noise

Images & Maps:

 

Purpose: Installation of a 14” PVC secondary waterline from Dunsinane Drive to 4800 W.

Duration: The installation of the secondary waterline will start on February 17, 2020. Completion of the project is expected late Spring 2020.

Impact: There will be a lane shift and restricted turns at the intersection of 4000 W and 10200 S on February 19, 2020 from 9:00 AM – 5:00 PM. Please expect some traffic delays on minor collector roads, the potential for hazards, and daytime noise.

Funding: Water Fund

Images & Maps:

 

Purpose: Replace transite pipeline with new PVC pipeline

Duration: Mill and overlay of Bonanza Circle, Bonanza Way, and Bonanza Court will take place Spring 2020. Installation of the waterline on Horseshoe Circle will resume Spring 2020.

Location: Bonanza Circle and Horseshoe Circle

Impacts: Minor traffic issues, potential hazards, daytime noise

Funding: Water fund

Maps & Images:

Purpose: To construct 6 new pickleball courts, install restrooms and upgrade the pavilion at City Park

Duration: Completion scheduled for Spring 2020

Location: City Park

Impacts: The construction areas are fenced, so the pavilion and existing playground are not available for use.

Maps & Images:

Purpose: A new traffic signal will be installed to improve efficiency and safety for pedestrians and motorists.

Duration: Construction is scheduled to begin January 6, 2020 and end Mid-February 2020.

Location: Daybreak Parkway and Lake Run Road Intersection

Funding: Federal Funding

Impacts: Crews will work Monday through Friday from 7 a.m. to 5 p.m., with occasional weekend work. During construction pedestrians pathways will be impacted at the northwest and southwest portions of the intersection. Pedestrians should expect to use designated detour routes to avoid these construction areas. Drivers should expect reduced travel lanes, lane shifts and possible temporary closures.

Maps & Images:

Purpose: South Valley Sewer District is installing a 15” sewer line.

Duration: Construction will begin January 24, 2020 and end approximately on February 24, 2020.

Location: River Heights Dr. from 10400 S to 10534 S

Impacts: Temporary traffic signals will be in place allowing one way traffic north and south.  This traffic control setup will be in place until February 26, 2020.

Maps & Images:

Purpose: Installation of 42″ steel waterline by Jordan Valley Water Conservancy District in 10200 South from Dunsinane Dr. to approximately 5700 West.

Duration: Construction will begin February 18, 2020 and end approximately August 2020.

Location: 10200 S from Dunsinane Dr. to 4000 W (first section of project)

Impacts: Beginning Tuesday, February 18, 2020 this section of road will be closed during the day and at night there will be one lane open with a temporary signal. Traffic lights will be placed by the contractor and moved accordingly to create a work safety zone. Drivers and pedestrians shall use caution while traveling in a work zone. Please expect some traffic delays on minor collector roads, the potential for hazards, and daytime noise. This section will take approximately 3-4 weeks to complete.

Images & Maps:

Purpose: Gough Construction will be closing Kestrel Rise Road between Dock Street & Split Rock Drive for a subdivision development.

Duration: February 24th to February 28th

Location: Kestrel Rise Road between Dock Street & Split Rock Drive

Funding: NA

Impact: The closure will happen from February 24th to February 28th. The road will remain closed at night for the five days.

Images & Maps:

Purpose: Summit Line Construction is upgrading and rebuilding an existing transmission line.

Duration: February 25th

Location: 11000 S and Woodfield Drive, 11150 S and 1494 W, and 10760 S at the canal

Funding: NA

Impact: There will be several road closures. Each closure will be for approximately five hours at a time.

Images & Maps:

City Projects Map:

Stay up to date with all the South Jordan City Projects. Using the link below, you can click on the colored icons to find the name, description and status of all the active projects in the City.
Projects Map