Construction Projects

South Valley Sewer District’s River Bottom Weekly Project Update

 Upcoming Impacts

This week crews are not working onsite. The project schedule has been adjusted and the upcoming work will be near Riverfront Parkway.

Upcoming Schedule

Week of October 4

  • Crews will work between the Health Catalyst Building and the South Jordan City East Riverfront Pavilion on Riverfront Parkway to install a stretch of sewer lining.
    • This will require the closure of a few parking stalls in the parking lot
    • This work is anticipated to finish on Saturday, October 19
  • Crews will install sewer from 10600 South to the Bawarchi Restaurant parking area.
    • This work is anticipated to finish on Saturday, October 19

Week of October 11

  • Crews will begin work at 14532 South 1515 West Bluffdale
    • This work is anticipated to finish on Thursday, October 14

Week of October 18

  • Crews will install sewer in the Bawarchi Restaurant parking area on Riverfront Parkway.
    • This will impact the parking area and businesses will be notified of the impacts.
    • This work is anticipated to finish on Saturday, October 23

The schedule is subject to change given weather and other unforeseen impacts.

 

What to Expect

  • Work hours will be 24 hours a day, Monday through Friday.
  • Parking restrictions may be required. All restrictions will be posted no less than 2 days prior to taking effect and being enforced.
  • Lane closures throughout the area.
  • Driveway access will be maintained for each property.
  • Increased noise, dirt, and lighting.
  • Drivers are encouraged to follow all posted signage to ensure the safety of the public and crews.

REMAINING CONSTRUCTION ACTIVITIES 
Remaining Construction Activities for 2200 west – 9400 South to 11400 South are as follows:

Street Lights installed and operating by December 2021

Landscaping to be completed Spring/Summer 2021

Purpose: South Jordan City and the Utah Department of Transportation are reconstructing 2200 West between 9400 South and 11400 South to create a consistent corridor that will increase motorist and pedestrian safety and improve walkability. 

Improvements include:

  • 11’ lanes with a 13’ center median
  • Consistent curb, gutter, sidewalk, and a 5’ park strip
  • An improved storm drain system
  • Improved roadway shoulders

Images & Maps:

Stay Informed
The Public Information Team is available to answer questions or address concerns from the community. Please contact UDOT:

Hotline: 385.955.2846
Email: 2200west@utah.gov
Web: www.udot.utah.gov/go/2200west

City Projects Map:

Stay up to date with all the South Jordan City Projects. Using the link below, you can click on the colored icons to find the name, description and status of all the active projects in the City.
Projects Map